Companies could face charges up to £2,500 a day for disruptive roadworks in Oxfordshire
A new daily charge to tackle disruptive roadworks in Oxfordshire will be introduced in May, to encourage utility companies to finish works quickly and at less busy times.
Oxfordshire County Council will be getting a lane rental scheme, which allows them to charge up to £2,500 per day for work on the busiest roads at peak times.
Cllr Andrew Gant, cabinet member for transport management, said: “It is in everyone’s interests for utility companies to minimise the impact their work has on our highway network, and a lane rental scheme is one way to achieve this.
“If they know they are going to be charged for the length of time they spend there, it is an incentive to complete the job as swiftly as possible.


“We look forward to being able to implement it and reap the benefits for everyone in Oxfordshire.”
The scheme was granted permission from the Government in November after it applied for the scheme in 2023.
It will come into effect on May 5.
The aim of the scheme is to give companies an incentive to prioritise off peak times and complete the work as quickly as possible to reduce their costs, and to encourage greater use of technology to speed up work.
Anneliese Dodds, MP for Oxford East, previously welcomed the scheme and said it would encourage companies to “minimise disruption and work more efficiently”.
Only nine per cent of the county’s highways network would be deemed eligible for charges, and the council’s own roadworks will not be exempt.
Roads in the city that are affected include Botley Road, Cowley Road, Abingdon Road, Banbury Road, Woodstock Road, London Road and Marston Ferry Road.
A full list of roads within the lane rental scheme can be found on the county council’s website.
The council will be able to apply the charge during peak periods only, including weekends and bank holidays, except on Christmas Day and Boxing Day.
Emergency safety repairs will get a 48-hour grace period.
The council has already been operating a permit scheme for road and street works since 2020, and gets around 30,000 requests per year.